Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-364/2009/A,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A

 

Monthly Environmental Monitoring & Audit Report

 

- August 2011 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

16 September 2011


Table of contents         

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 8

1.1        Scope of the Report 8

1.2        Structure of the Report 8

2.     Project Background. 10

2.1        Background. 10

2.2        Scope of the Project and Site Description. 10

2.3        Division of the Project Responsibility. 11

2.4        Project Organization and Contact Personnel 12

3.     status of regulatory compliance. 17

3.1        Status of Environmental Licensing and Permitting under the Project 17

4.     Monitoring Requirements. 26

4.1        Noise Monitoring. 26

4.2        Air Monitoring. 27

5.     Monitoring Results. 30

5.1        Noise Monitoring Results. 30

5.2        Real Time Noise Monitoring Results. 33

5.3        Air Monitoring Results. 33

5.4        Waste Monitoring Results. 35

6.     Compliance Audit. 39

6.1        Noise Monitoring. 39

6.2        Real Time Noise Monitoring. 39

6.3        Air Monitoring. 40

6.4        Review of the Reasons for and the Implications of Non-compliance. 40

6.5        Summary of action taken in the event of and follow-up on non-compliance. 40

7.     Cumulative Construction Impact due to the Concurrent Projects. 40

8.     Environmental Site Audit. 42

9.     Complaints, Notification of Summons and Prosecution. 45

10.    Conclusion. 48


lIST OF TABLES

 

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Table 3.3      Summary of submission status under FEP-03/364/2009

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. 04/HY/2006

Table 3.5      Summary of submission status under FEP-04/364/2009/A

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.7      Summary of submission status under FEP-02/364/2009

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.9      Summary of submission status under FEP-01/364/2009

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.11    Summary of submission status under FEP-05/364/2009/A

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.13    Summary of submission status under FEP-06/364/2009/A

Table 3.14    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.15    Summary of submission status under FEP-07/364/2009/A

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no.  HY/2009/17

Table 5.2      Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006

Table 5.3      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.5      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.6      Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8      Air Monitoring Station for Contract no. HY/2009/17

Table 5.9      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10    Air Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Monitoring Station for Contract no. HY/2009/15

Table 5.13    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.14    Details of Waste Disposal for Contract no. HY/2009/17

Table 5.15    Details of Waste Disposal for Contract no. 04/HY/2006

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20    Details of Waste Disposal for Contract no. HY/2009/19

Table 8.1      Summary of Landscape Inspections for Contract no. HY/2009/18

Table 8.2      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.3      Summary of Environmental Inspections for Contract no. HY/2009/18

Table 8.4      Summary of Environmental Inspections for Contract no. HY/2009/19

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

lIST OF FIGUREs

 

Figure 2.1              Project Layout

Figure 2.2              Project Organization Chart

Figure 4.1              Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1        Environmental Mitigation Implementation Schedule

Appendix 4.1        Action and Limit Level

Appendix 4.2        Copies of Calibration Certificates

Appendix 5.1        Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2        Noise Monitoring Results and Graphical Presentations

Appendix 5.3        Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4        Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1        Event Action Plans

Appendix 6.2        Notification of Exceedance

Appendix 9.1        Complaint Log

Appendix 10.1      Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report – August 2011 specific for Environmental Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai Bypass. This report presents the environmental monitoring findings and information recorded during the period 28th July 2011 to 27th August 2011. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Sheet piling

·          Guide wall construction near PTI

·          Diaphragm wall

·          Emergency exit construction at MTR by-law area

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

·          Construction works were completed and a duly signed report on Completion of Works was issued by the Engineer dated on 1 March 2011.  In addition, acknowledge of FEP surrender was under preparation by the Contractor

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·          Pre-drilling works for SCL Protection Works and CWB.

·          Pre-bored H pilling works.

·          Ground treatment works for proposed diaphragm wall in SCL Tunnels Protection Works.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Tunnel bored pile works at WCR1 area

·          Diaphragm wall construction at WCR1 area

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Diaphragm wall preparation work at TS1 and TPCWAE

·          Trial trench work at Hung Hing Road and POC

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Steel fabrication of temporary platform

·          Erection of platform to enable marine pre-drilling

·          Marine Pre-drilling

·          Remove existing dolphin pier

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w – International Finance Centre Eastern and Western End of Podium on a weekly basis. One limit level exceedance was recorded at M1a - Harbour Road Sports Centre on 22 August 2011 during restricted hour. After checking contractors’ work schedules and investigation found that construction works were conducted with a valid CNP during monitoring and traffic noises as major noise sources contributed in the noise monitoring. Two limit level exceedances were recorded at M6 - HK Baptist Church Henrietta Secondary School on 10 & 16 August 2011 during day time. After checking contractors’ work schedules and investigation found that construction works were conducted with deployed noise barriers during monitoring and traffic noises as major noise sources contributed in the noise monitoring. It was considered that the exceedances were not related at M1a and M6. Also, three Action levels were recorded due to three recorded noise complaints on 30 July, 7 and 26 August 2011.

 

  1. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel (North Point Section) and Island Eastern Corridor Link. No monitoring was conducted during the mentioned periods. Also, no project related action and limit level exceedance was recorded in the reporting period.

 

Air Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w – International Finance Centre eastern and western wing on every six days basis. No action and limit level exceedance were recorded in the reporting period.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There were five environmental complaints received on 30 July, 7, 10, 17 and 26 August 2011. No further complaint was received after follow-up action and investigation.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02 in this reporting period. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

 

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Sheet piling

·          Diaphragm wall

·          Instrumentation at Man Yiu Street

·          Slip road construction between Man Kwong Street and Finance Street

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

·          Construction works were completed and a duly signed report on Completion of Works was issued by the Engineer dated on 1 March 2011.  In addition, acknowledge of FEP surrender was under preparation by the Contractor

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·    Pre-drilling works for both CWB and SCL Protection Works.

·    Preparatory works such as ground treatment, guide wall construction and plant establishment for the proposed diaphragm wall construction works within HKCEC1

·    Installation of all outstanding geochnical instrumentation for construction of CWB & SCL Protection Works.

·    Pre-boring the existing seawall for subsequent diaphragm wall construction.

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·    Tunnel bored pile and diaphragm wall construction works.

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·    Diaphragm wall construction at TS1 and TPCWAE

·    Construction of dewatering well at Hung Hing Road and POC

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

·    Preparation works  and removal of existing marine piles

·    Pre-drilling works for bored pile and Diaphragm wall

·    Marine Pre-drilling

·    Remove existing dolphin pier

·    Set up of Contractor’s site office at Oil Street

·    Temp. Traffic Diversion at Watson Road

 

Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period 28th July to 27th August 2011. The cut-off date of reporting is at 27th of each reporting month.

 

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements – summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Site Inspection – summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.      The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·          Tunnel control buildings and ventilation buildings;

·          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·          Associated road lighting, road signing, traffic control and surveillance system; and

·          Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     In the reporting month, Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HK/2009/01

Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

Project Manager

Mr. K. S. Law

9090 1378

2566 7522

Site Agent

Mr. Tony Au

 

9725 5874

Sub Agent

Mr. Johnny Wong

9725 5870

Chiu Hing Construction & Transportation Co. Ltd.

Contractor under Contract no. 04/HY/2006

Contract Manager

Mr. Frederick Tsui

2967 6363

2967 6366

Senior Site Agent

Mr. Alvin Ma

2967 6363

2967 6366

Environmental Consultant

Mr. Jimmy Cheng

2965 0898

2556 9172

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Paul Yu

9456 9819

2634 1626

Operation Manager

Mr Lau Yee Ching

9466 3918

Construction Manager

Mr Jerry Siu

9493 3664

Construction Manager

Mr Ricky Lai

9487 6549

Construction Manager

Mr KK Yuen

3498 1213

Environmental Officer (Compliance Manager)

Mr Andy Mak

9103 2370

Environmental Supervisor

Ms Kiwi Chan

6227 8840

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658-3002

2827 9996

Site Agent

Mr. Mak Kam Wing

3658-3044

Deputy Site Agent

Mr. Anthony Wu

3658-3004

Quality & Environmental Manager

Mr. C.P. Ho

3658-3000

Environmental Officer

Ms Flora Ng

 

3658-3064

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HY/2009/19

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Mr. Cheung Kit Cheung

6909 1555

Environmental Engineer

Mr. Simon Wong

9281 4346

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Brian Gillon

2214 7700

2140 6799

Deputy Site Agent

Mr. Desmond Sze

2214 7703

Environmental Officer

Mr. Anfernee Chow

2214 7721

Environmental Supervisor

Mr. Dennis Yu

2214 7738

Environmental Supervisor

Ryan Tsui

2214 7705

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Manager

Mr. M Y Wong

2823 7879

2566 2192

Site Agent

Mr. Simon Tang

3557 6358

Head of construction

Andrew Kwan

3557 6396

Environmental Officer

Samuel Tsui

3557 6347

Environmental Officer

Daniel Sin

3557 6215

Environmental Supervisor

Kelven Yip

3557 6347

Environmental Supervisor

Tim Fung

3557 6349

 

 

Environmental Supervisor

Hilda Lau

3557 6378

 

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

·          Construction works were completed and a duly signed report on Completion of Works was issued by the Engineer dated on 1 March 2011.  In addition, acknowledge of FEP surrender was under preparation by the Contractor

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Sheet piling

·          Guide wall construction near PTI

·          Diaphragm wall

·          Emergency exit construction at MTR by-law area

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·          Pre-drilling works for SCL Protection Works and CWB.

·          Pre-bored H pilling works.

·          Ground treatment works for proposed diaphragm wall in SCL Tunnels Protection Works.

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Tunnel bored pile works at WCR1 area

·          Diaphragm wall construction at WCR1 area

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Diaphragm wall preparation work at TS1 and TPCWAE

·          Trial trench work at Hung Hing Road and POC

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Steel fabrication of temporary platform

·          Erection of platform to enable marine pre-drilling

·          Marine Pre-drilling

·          Remove existing dolphin pier

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

·          Construction works were completed and a duly signed report on Completion of Works was issued by the Engineer dated on 1 March 2011.  In addition, acknowledge of FEP surrender was under preparation by the Contractor

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

·          ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Sheet piling

·          Diaphragm wall

·          Instrumentation at Man Yiu Street

·          Slip road construction between Man Kwong Street and Finance Street

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

·    Pre-drilling works for both CWB and SCL Protection Works.

·    Preparatory works such as ground treatment, guide wall construction and plant establishment for the proposed diaphragm wall construction works within HKCEC1

·    Installation of all outstanding geochnical instrumentation for construction of CWB & SCL Protection Works.

·    Pre-boring the existing seawall for subsequent diaphragm wall construction.

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·    Tunnel bored pile and diaphragm wall construction works.

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·    Diaphragm wall construction at TS1 and TPCWAE

·    Construction of dewatering well at Hung Hing Road and POC

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·    Preparation works  and removal of existing marine piles

·    Pre-drilling works for bored pile and Diaphragm wall

·    Marine Pre-drilling

·    Remove existing dolphin pier

·    Set up of Contractor’s site office at Oil Street

·    Temp. Traffic Diversion at Watson Road

 

status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

 

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

  4 Aug 2010

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Valid

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

3.1.3.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

N/A

Valid

Notification of Works Under APCO

319348

13 Jul 2010

N/A

Valid

Discharge Licence

WT00007212-2010

5 Aug 2010

5 Aug 2010 – 31 Aug 2015

Valid

Registration as a Waste Producer

5213-151-L2608-05

13 July 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010400

16 Mar 2010

N/A

Valid

 

Table 3.3    Summary of submission status under FEP-03/364/2009

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 September 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

1 September 2010

Condition 2.9

Noise Management Plan

1 September 2010

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-04/364/2009/A for contract no. 04/HY/2006 are shown in Table 3.4 and Table 3.5.

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. 04/HY/2006

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

N/A

Valid

Notification of Works Under APCO

322225

7 Oct 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7005123

9 Mar 2007

N/A

Valid

 

 

 

 

 

 

Table 3.5       Summary of submission status under FEP-04/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 July 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

11 July 2010 and

5 August 2010

Condition 2.9

Noise Management Plan

19 October 2010

Condition 2.10

Landscape Plan

26 November 2010

 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0107-11

8 Feb 2011

16 Mar 2011 to 15  Sep 2011

Valid

 

GW-RS0384-11

29 Apr 2011

27 May 2011 to 26  Nov 2011

Valid

 

GW-RS0680-11

22 Jul 2011

29 Jul 2011 to 19 Jan 2012

Valid

 

GW-RS0689-11

28 Jul 2011

29 Jul 2011 to 28 Jan 2012

Valid

Discharge Licence

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.7    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

18 May 2011

Special Conditions, Clause 2.6

Commencement Date of Works

25 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

10 Jun 2011

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.6.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.

Table 3.8    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0011-11

27 April 2011

1 June 2011 to

30 Nov 2011

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0716-11

2 Aug 2011

12 Aug 2011 to 11 Feb 2012

Valid

 

GW-RS0722-11

2 Aug 2011

5 Aug 2011 to 5 Oct 2011

Valid

 

GW-RS0723-11

12 Aug 2011

15 Aug 2011 to 14 Feb 2012

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0335-11

8 April 2011

11 Apr 2011 to 30 Sept 2011

Cancel

 

GW-RS0343-11

11 April 2011

25 Apr 2011 to 10 Oct 2011

Valid

 

GW-RS0369-11

21 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RS0377-11

27 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RE0311-11

4 May 2011

5 May 2011 to 31 Oct 2011

Valid

 

GW-RS0401-11

3 May 2011

18 May 2011 to 17 Nov 2011

Valid

 

GW-RS0414-11

3 May 2011

9 May 2011 to 8 Nov 2011

Valid

 

GW-RS0423-11

9 May 2011

22 May 2011 to 21 Nov 2011

Valid

 

GW-RS0430-11

9 May 2011

16 May 2011 to 15 Nov 2011

Cancel

 

GW-RS0453-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0458-11

17 May 2011

21 May 2011 to 20 Nov 2011

Cancel

 

GW-RS0461-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0473-11

27 May 2011

01 May 2011 to 30 Nov 2011

Cancel

 

GW-RS0496-11

31 May 2011

07 Jun 2011 to 06 Dec 2011

Valid

 

GW-RS0502-11

8 Jun 2011

13 Jun 2011 to 12 Dec 2011

Valid

 

GW-RS0579-11

22 June 2011

17 July 2011 to 16 Jan 2012

Valid

 

GW-RS0645-11

18 July 2011

22 Jul 2011 to 21 Jan 2012

Valid

 

GW-RS0649-11

22 July 2011

1 Aug 2011 to 31 Jan 2012

Valid

 

GW-RS0691-11

25 July 2011

27 July 2011 to 26 Jan 2012

Valid

 

GW-RS0716-11

2 Aug 2011

12 Aug 2011 to 11 Feb 2012

Valid

 

GW-RS0722-11

2 Aug 2011

5 Aug 2011 to 5 Oct 2011

Valid

 

GW-RS0723-11

12 Aug 2011

15 Aug 2011 to 14 Feb 2012

Valid

Discharge Licence

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

 

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

 

WT00006673-2010

14 May 2010

31 Mar 2015

Valid

 

WT00006757-2010

28 May 2010

31 May 2015

Valid

 

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

 

WT00008982-2011

26 April 2011

30 April 2016

Valid

 

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

 

Table 3.9    Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

14 Jun 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

14 Jun 2011

Special Conditions, Clause 2.6

Commencement Date of Works

21 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

28 Jun 2011

Condition 2.11

Landscape Plan

23 Aug 2011

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

3.1.7.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.10 and Table 3.11.

Table 3.10  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

N/A

Valid

Notification of Works Under APCO

322293

07 Oct 2010

N/A

Valid

Discharge Licence

WT00008229-2011

13 Jan 2011

31 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance

7011587

11-Oct-10

N/A

Valid

Registration as a Waste Producer

WPN: 8335-121-L1048-04

17 Dec 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0795-11

24 Aug 2011

24 Aug 2011 21:00 –

21 Jan 2012 06:00

Valid

 

GW-RS0690-11

27 Jul 2011

27 Jul 2011 21:00 –

24 Aug 2011 21:00

Expired

 

Table 3.11  Summary of submission status under FEP-05/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

01 March 2011

Condition 2.10

Landscape Plan (Rev. 4)

3 August 2011

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.8.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.12 and Table 3.13

Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN: 5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

N/A

Valid

Water Discharge Licence (Discharge at  Portion VII)

WT00008780-2011

22 Mar 2011

22 Mar 2011 to 31 Mar 2016

Valid

Water Discharge Licence (Discharge at  Hung Hing Road)

WT00008905-2011

11 Apr 2011

11 Apr 2011 to 30 Apr 2016

Valid

Construction Noise Permit (CNP) for Installation of Instrumentation

GW-RS0727-11

11 Aug 2011

24 Aug 2011 to

23 Feb 2012

Valid

Construction Noise Permit (CNP) for Site Office Generator (24 hr)

GW-RS0220-11

16 Mar 2011

16 Mar to

15 Sep 2011

Valid

Construction Noise Permit (CNP) for Diaphragm Wall Construction

GW-RS0308-11

1 Apr 2011

4 Apr to

27 Sep 2011

Valid

Construction Noise Permit (CNP) for Diaphragm Wall Construction

GW-RS0710-11

3 Aug 2011

5  Aug 2011 to

1 Feb 2012

Valid

Construction Noise Permit (CNP)

GW-RS0168-11

21 Feb 2011

24 Feb 2011 to

23 Aug 2011

Expired

Construction Noise Permit (CNP)

GW-RS0749-11

11 Aug 2011

15 Aug 2011 to

7 Feb 2012

Valid

 

Table 3.13  Summary of submission status under FEP-06/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 Mar 2011

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule

15 Mar 2011

Condition 2.8

Location Plan

15 Mar 2011

Condition 2.23

Noise Management Plan

6 May 2011

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

3.1.9.     The current status on licences and/or permits on environmental protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.14 and Table 3.15.

Table 3.14  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

N/A

Valid

Notification of Works Under APCO

326160

24 Jan 2011

N/A

Valid

Registration as a Waste Producer

7012306

10 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

N/A

Valid

Application for Vessel Disposal

7012306

21 July 2011

N/A

Valid

 

Table 3.15  Summary of submission status under FEP-07/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

02 Jun 2011

Condition 2.13

Landscape Plan

7 July 2011

Monitoring Requirements

4.1          Noise Monitoring

Noise Monitoring Stations

4.1.1.     The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1.  Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

Real time Noise Monitoring Stations

4.1.2.     Review of feasibility on the real time noise monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was found not appropriate to be a monitoring station for monitoring the IECL Piling works and Demolition after visited. 

4.1.3.     The noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Real Time Noise Monitoring Stations

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.4.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.5.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.6.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

4.1.7.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.8.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.9.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.10.   The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements July be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.2          Air Monitoring

Air Quality Monitoring Stations

4.2.1.     The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3    Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Garden opposite to Pedestrian Plaza

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (western End of Podium)

Central

Remarks: As per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 – 1.7 m3 per minute adjustable flow range;

·          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          Capable of providing a minimum exposed area of 406 cm2;

·          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          Equipped with a shelter to protect the filter and sampler;

·          Incorporated with an electronic mass flow rate controller or other equivalent devices;

·          Equipped with a flow recorder for continuous monitoring;

·          Provided with a peaked roof inlet;

·          Incorporated with a manometer;

·          Able to hold and seal the filter paper to the sampler housing at horizontal position;

·          Easily changeable filter; and

·          Capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     Filter paper of size 8” x 10” shall be abelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.9.     After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.   All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.   Current calibration certificates of equipments are presented in Appendix 4.2.

Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.     In the reporting month, the concurrent contracts are as follows:

Ÿ  Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Ÿ  Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

Ÿ  Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

Ÿ  Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009

Ÿ  Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

Ÿ  Contract no. HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai East

5.0.3.     The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1          Noise Monitoring Results

5.1.1.     The noise monitoring at stations were M1a and M5b during day time, M1a, M7e and M7w during restricted hour were rescheduled on 11 July 2011 due to rain.

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

5.1.2.     The proposed division of noise monitoring stations for Contract no. HY/2009/17 are summarized in Table 5.1 below:

Table 5.1    Noise Monitoring Stations for Contract no.  HY/2009/17

Station

Description

M4b

Victoria Centre

 

5.1.3.     No action and limit level exceedance was recorded during day time and restricted hour period in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

5.1.4.     Construction activity under contract no. 04/HY/2006 was completed, no noise monitoring for the contract was conducted. Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 and 04/HY/2006 are summarized in Table 5.2 below:

Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006

Station

Description

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

5.1.5.     One action level exceedance was recorded due to a recorded noise complaint on 30 July 2011 for the contract of HY/2009/18 and no limit level exceedance was recorded during day time and restricted hour period in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2 and the complaints can be referred in Appendix 9.1. 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.1.6.     The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.7.     No noise monitoring for Contract no. HK/2009/01 was conducted in this reporting month. However, noise monitoring was conducted for Contract no. HK/2009/02 in the reporting month

5.1.8.     One action level and one limit level exceedance was recorded at M1a – Harbour Road Sports Centre due to a recorded noise complaint on 26 August 2011 for the contractor of HK/2009/01 and on 22 August 2011 during restricted hour for the contractor of HK/2009/02. Major noise source was contributed from Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool. Details of the Notification of Exceedance can be referred in Appendix 6.2. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2 and the complaints can be referred in Appendix 9.1. 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.1.9.     The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011. The proposed division of noise monitoring stations are summarized in Table 5.4 below.

 

Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

5.1.10.   One action level exceedance and no limit level exceedance was recorded during day time and restricted hour period due to a recorded noise complaint on 7 August 2011 in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2 and the complaints can be referred in Appendix 9.1. 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 

5.1.11.   Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.5 below.

Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

5.1.12.   No action level and two limit level exceedances were recorded at M6 – HK Baptist Church Henrietta Secondary School on 10 and 16 August 2011 during day time period. After checking contractor’s work schedules and investigation found that traffic noises in IECL as major noise sources contributed in the noise monitoring. It was considered the exceedances were not related to the project. Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2 and details of the Notification of Exceedance can be referred in Appendix 6.2.   

5.2          Real Time Noise Monitoring Results

5.2.1.     No construction activity with valid Construction Noise Permit was conducted during night time period (2300 to 0700) in this reporting month.

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

5.2.2.     The proposed division of noise monitoring stations are summarized in Table 5.6 below. Real time noise monitoring for the piling works under contract no. HY/2009/17 was commenced on 5 October 2010

Table 5.6    Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.3.     No project related action and limit level exceedance were recorded in the reporting period. Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.2.4.     The proposed division of noise monitoring stations are summarized in Table 5.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 5.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

RTN2

North Point

Oil Street Community Liaison Center

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.5.     No project related action and limit level exceedance were recorded in the reporting period. Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.3          Air Monitoring Results

5.3.1       Due to lack of electricity supply at station CMA1b, CMA2a CMA4a, the 24 hr-TSP monitoring were rescheduled to conduct on 2 August 2011, 19 August 2011, 8 August 2011 and 25 August 2011.

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

5.3.1.     The proposed division of air monitoring stations are summarized in Table 5.8 below. Air monitoring for the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.

Table 5.8    Air Monitoring Station for Contract no. HY/2009/17

Station

Description

CMA2a

Causeway Bay Community Centre

5.3.2.     No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

5.3.3.     Construction activity under contract no. 04/HY/2006 was completed, no air monitoring for the contract was conducted. Air monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.The proposed division of air monitoring stations are summarized in Table 5.9 below.

Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

5.3.4.     No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

5.3.5.     The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. Only 1-hr TSP monitoring was conducted in the reporting period. The proposed division of air monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.3.6.     The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air monitoring stations are summarized in Table 5.11 below.

Table 5.11 Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

5.3.7.     No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.3.8.     The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table 5.12 below.

Table 5.12 Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

5.3.9.     The proposed division of air monitoring stations are summarized in Table 5.13 below. Air monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.

Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil St Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.10.   No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

 

5.4          Waste Monitoring Results

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

5.4.1.     No Inert C&D waste was recycled in the reporting month. Details of the waste flow table are summarized in Table 5.14

Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17

Waste Type

Quantity this month, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

1354.82

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

N/A

N/A

N/A

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

5.4.2.     No inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.15.

Table 5.15  Details of Waste Disposal for Contract no. 04/HY/2006

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

1288.5

Chai Wan and

T.K.O. 137

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract nos. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

5.4.3.     Inert and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.16.

Table 5.16  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type*

Quantity this month, m3

Cumulative-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

206.67

206.67

TKO137

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

35.92

35.92

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.4.4.     Inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.17.

Table 5.17  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

14,763

29,259

TM 38

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

1,104

1,104

N/A

Contractor clarified that no Inert and Non-inert C&D materials disposed in June 2011

 

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

5.4.5.     Inert C&D and Non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.18.

Table 5.18  Details of Waste Disposal for Contract no. HY/2009/18

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

15.9

3962.4

T.K.O. 137

Inert C&D materials recycled

0

58.5

N/A

Non-inert C&D materials disposed

7.2

152.0

SENT Landfill

Non-inert C&D materials recycled

0

0

N/A

Chemical waste disposed

0

0

N/A

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.4.6.     Non-inert C&D waste was disposed and recycled of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

1,952

Tuen Mun Area 38

Inert C&D materials recycled

29

29

N/A

Non-inert C&D materials disposed

12.0

38.1

SENT Landfill

Non-inert C&D materials recycled

61.3

61.3

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.4.7.     Inert and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

Table 5.20  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

0.115

1.805

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

Compliance Audit

6.0.1.     The Event Action Plan for construction noise, air qualities are presented in Appendix 6.1.

6.1          Noise Monitoring

 

Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

6.1.1.     No exceednace was recorded in the reporting month.

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

6.1.2.     No noise monitoring was undertaken in the reporting month.

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

6.1.3.     One action level and no limit level exceedance was recorded due to a recorded noise complaint on 30 July 2011 in the reporting month.

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention Exhibition Centre – Tunnel Works under FEP-02/364/2009

 

6.1.4.     No noise monitoring for Contract no. HK/2009/01 was conducted in this reporting month.

6.1.5.     One action level exceedance was recorded at M1a – Harbour Road Sports Centre due to recorded noise complaint on 26 August 2011.

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.1.6.     One limit level and no action level exceedance were recorded at M1a – Harbour Road Sports Centre on 22 August 2011 during restricted hour. Investigation found that major traffic noise was contributed in the noise monitoring and not related to the Project.

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

6.1.7.     One action level exceedance and no limit level exceedance was recorded during day time and restricted hour period due to a recorded noise complaint on 7 August 2011 in the reporting month.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.8.     Two limit level and no action level exceedances were recorded at M6 – HK Baptist Church Henrietta Secondary School on 10 and 16 August 2011 during day time period. After checking contractor’s work schedules and investigation found that no major construction works was conducted during monitoring on 10 August 2011 and per drilling work was conducted with noise barrier deployed and traffic noises in IECL as major noise sources contributed in the noise monitoring. It was considered the exceedance was not related to the Project.

6.2          Real Time Noise Monitoring

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

6.2.1       No exceednace was recorded in the reporting month.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.2.2       No exceednace was recorded in the reporting month.

6.3          Air Monitoring

 

Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009

6.3.1.     No exceedance was recorded in the reporting month.

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

6.3.2.     No air quality monitoring was undertaken in the reporting month.

Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

6.3.3.     No exceednace was recorded in the reporting month.

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009

6.3.4.     No exceednace was recorded in the reporting month.

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.3.5.     No exceednace was recorded in the reporting month.

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

6.3.6.     No exceednace was recorded in the reporting month.

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.3.1       No exceednace was recorded in the reporting month.

6.4          Review of the Reasons for and the Implications of Non-compliance

6.4.1.     There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.5          Summary of action taken in the event of and follow-up on non-compliance

6.5.1       There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.

Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-364/2009/A, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     From the Monthly EM&A report (July 2011) of Central Reclamation Phase III the key works in August 2011 are as follows:

·    Type A filling in FRAW and FRAE above +2.5mPD

·    General filling works above +2.5mPD in IRAE

·    Surcharging in FRAW and FRAE

·    Installation of removable panels at caisson

·    Installation of remaining seawall blocks and retaining wall on the west side of culvert F

·    Construction of storm and foul drainage and gullies in hinterlands for Road P2 and Road D9

·    Roadworks for Road P2

·    Construction of GPO boundary wall

·    Construction of PLA boundary wall and entrance

·    Construction of Promenade enhancement works

·    Construction of buildings at PLA berth

·    Road P2 Underpass structures

·    Construction of CWB structure

·    Backfilling and waterproofing works for CWB structure

·    Importation of fill material

·    Strengthening of Man Yiu Street Footbridge

7.0.3.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II was the seawall block construction at TCBR1w, reclamation works of HKCEC Water Channel, dredging for submarine outfall pipe, Advanced piling works at FEHD Whitfield Depot, Central Interchange, cross-harbour water mains and marine pre-drilling in the reporting month. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activity were advance piling works at FEHD Whitfield Depot, sheet piling and pre-drilling works at Central, marine pre-drilling at North Point in the reporting month and tunnel works at Wan Chai East.

7.0.4.     The major environmental impacts generated from advanced piling works at FEHD Whitfield Depot were undertaken and sheet piling, pre-drilling and sheet piling works at Central and tunnel works at Wan Chai East in the reporting month. No significant air impact was anticipated in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II was mainly insignificant.

Environmental Site Audit

8.0.1.     During this reporting month, weekly environmental site audits were conducted for Contracts no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19 and HK/2009/02. No non-conformance was identified during the site audits.

8.0.2.     A landscape inspection was conducted for Contractors HY/2009/18 on 22 August 2011. No observation was recorded in this inspection. The results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1    Summary of Landscape Inspections for Contract no. HY/2009/18

Item

Date

Observations

Action taken by Contractor

Outcome

110822_01

22-Aug-11

The contractor was reminded to pay more attention for staking & watering of Tree 1356

Pay more attention for staking & watering of Tree 1356

Noted by Contractor

8.0.3.     Four site inspections for Contract no. HY/2009/15 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.2.

Table 8.2    Summary of Environmental Inspections for Contract no. HY/2009/15

Item

Date

Observations

Action taken by Contractor

Outcome

110802_01

2-Aug-11

Waste water that is generated by mini-piling shall be collected and treated before discharged.

Treating the wastewater before discharge

Completion as observed on 9-Aug-11

110802_02

2-Aug-11

Drain hole of the drip trays shall be plugged

Plugging the drain hole of the drip tray

Completion as observed on 9-Aug-11

110802_03

2-Aug-11

Cements that are over 20 packs shall be covered well by tarpaulin.

Covering the cement bags with tarpaulin sheet

Completion as observed on 16-Aug-11

110809_01

9-Aug-11

The contractor was reminded that stagnant mud and water inside drip tray shall be cleared. It should be treated as chemical waste if oil spilled in them.(Abutment A)

Removal of the water and mud from drip tray and handling as chemical waste

Completion as observed on 16-Aug-11

110809_02

9-Aug-11

The contractor was reminded that Stockpiles at TS4 should be covered.

Covering the stockpile with tarpaulin sheet

Completion as observed on 16-Aug-11

110809_03

9-Aug-11

The contractor was reminded that enclosure of batching plant should be maintained at Abutment A.

Proving an enclosure to the batching plant

Completion as observed on 16-Aug-11

110816_01

16-Aug-11

Overflow of waste water was found at the pre-treat tank. The contractor was reminded to increase the volume.

Improvement of the design of the pre-treatment tank

Completion as observed on 23-Aug-11

110816_02

16-Aug-11

Drip tray shall be provided for chemical (Chlorine) storage.

Proving the drip tray to the chemical

Completion as observed on 23-Aug-11

110816_03

16-Aug-11

Water spraying shall be conducted at EXTCPWA.

Water spraying on the dusty surface

Completion as observed on 23-Aug-11

110823_01

23-Aug-11

The contractor was reminded that collect floating refuses near TS4 and TS1.

Removal of the floating refuse

Completion as observed on 23-Aug-11

110823_02

23-Aug-11

The contractor was reminded that tidy up the haul road outside the construction site (Hing Fat Street)

Tidying up the haul road

Completion as observed on 30-Aug-11

110823_03

23-Aug-11

The contractor was reminded that increase the water spraying more frequently in the sunny day.

Water spraying on the dusty surface

Completion as observed on 30-Aug-11

 

8.0.4.     Four site inspections for Contract no. HY/2009/17 were carried out during this reporting period. No observation was recorded in this reporting month.    

8.0.5.     Five site inspections for Contract no. HY/2009/18 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3    Summary of Environmental Inspections for Contract no. HY/2009/18

Item

Date

Observations

Action taken by Contractor

Outcome

110728_01

28-Jul-11

The contractor was reminded to inspect the enclosure of grouting plant in good condition before grouting works began

Inspect the enclosure grouting works began

Completion as observed on 4 Aug 2011

110811_01

11-Aug-11

Drain hole of the drip trays shall be plugged

Plugging the drain hole of the drip tray

Completion as observed immediately

8.0.6.      Four site inspections for Contract no. HY/2009/19 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.4.

Table 8.4    Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Outcome

110803_01

3-Aug-11

The contractor was reminded to tie the silt curtain at portion 40 tightly.

To tie the silt curtain tightly.

Completion as observed on 10-Aug-11

110810_01

10-Aug-11

Muddy water was observed discharging through V channels to open channel T at the reclamation area. The as-built desilting measures shall be improved.

Improve the desilting measures at channel T

Completion as observed on 17-Aug-11

110810_02

10-Aug-11

The contractor was reminded to remove the stagnant water inside drip tray.

Removal of the water and mud from drip tray

Completion as observed on 17-Aug-11

110817_01

17-Aug-11

Drain hole of the drip trays shall be plugged

Plugging the drain hole of the drip tray

Completion as observed on 24-Aug-11

110824_01

24-Aug-11

The contractor was reminded to conduct water spraying at Portion VII.

Conduct water spraying

Completion as observed on 30-Aug-11

8.0.7.     As construction works for Contract no.04/HY/2006 were completed, no site inspection was carried out since February 2011. 

8.0.8.     No site inspections for Contract no. HK/2009/01 was carried out during this reporting period as the commencement date of the project was on 25 August 2011.

8.0.9.     Four site inspections for Contract no. HK/2009/02 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.5.

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

110728_01

28-Jul-11

Existing silt curtain for filling is insufficient to mitigate the water quality impact. Frame type silt curtain with adequate shall be provided.

Providing the proper silt curtain for the filling

Completion as observed on 4-Aug-11

110728_02

28-Jul-11

Silt at the vehicle wheel washing facility (Gate 1) shall be removed regularly.

Regular removal of the silt at the wheel washing facility

Completion as observed on 4-Aug-11

110728_03

28-Jul-11

Stockpile of C&D stockpile located at Wan Shing Street shall be covered with tarpaulin sheet.

Leveling down and cover the stockpile.

Completion as observed on 4-Aug-11

110804_01

4-Aug-11

A shelter with 3-sides and cover shall be provided for the grouting mixer. Also, sand bags shall be provided in the edge of grouting area.

Providing the proper shelter when grouting mixing. Sand bags were placed in the grouting area.

Completion as observed on 11-Aug-11

110804_02

4-Aug-11

Regular water spraying shall be applied on the dusty surface at Finger Pier.

Spraying water on the dusty surface

Completion as observed on 11-Aug-11

110817_01

17-Aug-11

Oil leakage was observed from the excavator at Wan Shing Street. Maintenance works for the excavator shall be provided.

Maintenance of the excavator and clearance of the oil stain.

Completion as observed on 25-Aug-11

110825_01

25-Aug-11

Silt curtain at western seawall shall be maintained in proper condition.

Maintenance of the silt curtain in proper condition.

Completion as observed on 1-Sept-11

110825_02

25-Aug-11

Drip tray shall be provided to the oil drums near Gate 1 at WCR 1.

Placement of the drip tray underneath the oil drums

Completion as observed on 1-Sept-11

 

Complaints, Notification of Summons and Prosecution

9.0.1.     There were five complaints received in the reporting month.

9.0.2.     A noise impact complaint ICC complaint no.1-305074350 by Mr. TSUI on 30 July 2011 referred by RSS to Environmental Team on 1 August 2011. He complained on the construction noise generated by the construction operations of Central-Interchange which is near the spa room. In addition, Mr. TSUI enquired the commencement time of the construction on Saturday. RSS confirmed the noisiest plant from 2 vibratory hammers has been conducted in alternating manner for sheet piling works to minimize noise due to current plant operation as one of the mitigation measures implemented by contractor for noise reduction. Further investigation revealed that no construction noise exceedance was recorded at noise monitoring station of IFC Western End of Podium on 25 July 2011 and 4 August 2011 during daytime period while sheet piling and excavation works were undertaken during monitoring. No further complaint from complainant was received after the liaison. In conclusion, it was related to the construction works under Contract HY/2009/18 and mitigation measure was provided.

9.0.3.     A noise impact complaint ICC complaint no.1-304615409 by Ms. Chiu on 27 July 2011 referred by RSS to Environmental Team on 28 July 2011. She complained on the construction noise generated from the construction operations of Central-Wanchai Bypass in morning at 7am rather than at noon. RSS confirmed to start the rock breaking activities at 8m as a mitigation measure to minimize the noise nuisance in the vicinity of the residents. Further investigation revealed that no construction noise exceedance was recorded at noise monitoring station of Victoria Centre on 4 and 10 August 2011 during daytime period while breaking and excavation works were undertaken during monitoring. However, complainant did not satisfy with the response on the noise nuisance from the rock-breaking during morning in front of Victoria Centre and then further complained via 1823 on 7 August 2011. Highways contacted the complainant on 15 August 2011 that the noisy rock breaking operation had been completed. No further complaint from complainant was received after the liaison. In conclusion, it was related to the construction works under Contract HY/2009/15 and mitigation measure was provided.

9.0.4.     An ICC complaint no. 1 – 306740207 was received on 10 August 2011. The complainant, Mr. Yip complained that muddy water was discharged from work site to the seafront near Oil Street during heavy rain. According to the Hong Kong Observatory, there was amber rainstorm on August 2011. Confirmed with RE, muddy water was caused by a heap of earth being washed to the sea by heavy rain. The heap of earth was referred as a small stockpile placed close to the seafront in front of Oil Street within the site area under handover transition period from contract HY/2009/11 to contract HY/2009/19. The necessary mitigation measures to protect the small stockpile against rainfall were missing at the time of complaint.

9.0.5.     A visual complaint, ICC no. 1-307657681, was received on 23 August 2011. The complainant from City Garden complained that nuisance generated by light from a large amount of spot-lights on the barge during mid-night on 17 August 2011 in 0100 hrs. Confirmed with RE, due to the safety reason, flood lights shall be provided and functioned on the barge in accordance with the provisions of the Merchant Shipping (Safety) Ordinance to prevent collisions and some non-essential lights were turned on during night-time period. Investigation found that these lights caused the nuisance to the nearby residents. Highways contacted the complainant on 17 August 2011 explaining the necessity of the lighting and requested the contractor of HY/2009/19 to switch off all non-essential lights to minimize nuisance to the nearby residents. A follow-up contact was made by Highways again on 18 August 2011 to confirm the efficiency of the mitigation measure and arrangement. The complainant was satisfied with them and no further complaint was received after that. In conclusion, it was related to the construction works under Contract HY/2009/19 and mitigation measure was provided.

9.0.6.     A noise complaint was raised by Grand Hyatt and a complainant via 1823 on 26 August 2011 regarding construction noise and vibration nuisance generated from the works at Convention Avenue and inside the HKCEC1 reclamation area. Confirmed with the Resident Site Staff, the construction works were referred to the Contractor HK/2009/01 and the excavator mounted breaker at Convention Avenue and drilling rig at HKCEC1 reclamation area were the dominant construction noise source during this period. The drilling rig at HKCEC1 reclamation area and excavator mounted breaker at Convention Avenue were then temporary suspended after received the complaint.

9.0.7.     Investigation revealed that the erected noise barriers (4m cantilevered movable noise barrier for the drilling rig and 1m movable noise barrier for the excavator mounted breaker) were not located close to the plants to provide adequate noise screening. Contractor was advised to avoid concurrent operation of construction plants at site. Further enhancement of movable noise barriers at HKCEC1 and providing noise enclosure for the excavator mounted breaker at Convention Avenue are needed. Further investigation and checking on 31 August and 7 September 2011 revealed that the implemented noise mitigation measures were in proper and minimize the noise impact.

9.0.8.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.9.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

August 2011

5

Sep 10 to July 11

4

Total

9

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

10.        Conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.   The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1     Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/15

·         Diaphragm wall construction at TS1 and TPCWAE

·         Construction of dewatering well at Hung Hing Road and POC

·         Watering any dust generating activities

·         Checking all drip trays frequently and clear any stagnant water and mud inside it.

HY/2009/17

·         ELS works for basement construction for pile cap construction.

·         Noise barrier shall be implemented; and

·         Watering any dust generating activities

HY/2009/18

·         Instrumentation Manholes and Intake Culvert Survey

·         Excavation of trial pit

·         Hoarding erection

·         Tree transplanting

·         Installation of coupler in CR3

·         Drainage diversion works

·         Site investigation and pre-drilling works

·         Excavation in Trough B

·         Sheet piling

·         Diaphragm wall

·         Instrumentation at Man Yiu Street

·         Slip road construction between Man Kwong Street and Finance Street

·         Noise barrier shall be implemented; and

·         Noise level shall be controlled by reducing piling rate and no. of plants working in parallel.

·         Dust control during dust generating works

HY2009/19

·         Steel fabrication of temporary platform

·         Erection of platform to enable marine pre-drilling

·         Marine pre-drilling

·         Remove existing dolphin pier

·         Noise level shall be controlled by reducing drilling rate.

·         Noise barrier shall be deployed for dolphin pier removal.

HK2009/01

·         Pre-drilling works for SCL Protection Works and CWB.

·         Pre-bored H pilling works.

·         Ground treatment works for proposed diaphragm wall in SCL Tunnels Protection Works.

·          

·         Noise level shall be controlled by reducing pilling rate.

·         Well maintain the enclosures for grouting and bentonite mixing plants.

HK/2009/02

·         Tunnel bored pile and diaphragm wall construction works.

·         Noise level shall be controlled by reducing pilling rate.

·         Well maintain the enclosures for grouting and bentonite mixing plants.

 

10.0.3.   Construction works were completed and a duly signed report on Completion of Works was issued by the Engineer dated on 1 March 2011.  In addition, acknowledge of FEP surrender was under preparation by the Contractor